How long does a bathroom renovation take?

Allow about six weeks for a complete new bathroom, from measuring up to handover. For five of them you won't have a working bathroom. Most of the work takes a few days per step; what makes the planning long is the order and the drying time in between.

The short answer

  • A complete new bathroom, with a walk-in shower and tiles from floor to ceiling: about 6 weeks.
  • Tiling only the shower area: about 5 weeks.
  • Freshening up (new taps and toilet, new grout, painting): 2 to 3 weeks.

Those weeks come from the example plan PLOTT makes for a bathroom with a builder you've already chosen. If you still need to find one, add a week for quotes, and bear in mind that a good builder often can't start next week.

Where does the time go?

With a kitchen you mostly wait for the delivery. With a bathroom the time is in the order: each trade builds on the work of the one before, and in between, things have to dry.

Week 1Week 6
Measure up and decide the layout
2 days
Take out old sanitary ware and tiles
5 days
Ventilation, pipes and electrics
4 days
Fit shower drain and waste
1 day
Prepare walls and floor
3 days
Drying
3 days
Waterproofing
1 day
Drying
1 day
Tile walls and floor
8 days
Drying
1 day
Grouting
1 day
Fit toilet, basin and taps
2 days
Fit shower screen
1 day
Finish the snagging list
1 day
WaitingExample: a complete new bathroom with a walk-in shower, fully tiled. In calendar days, weekends included.

Step by step

1. Measuring up and deciding the layout: 2 days

Where do the shower, toilet and basin go? If everything stays where it is, so do the pipes. If you move the toilet or the shower, the waste has to move with it, and your floor needs to allow for that.

2. Taking it out: 3 working days

The old sanitary ware comes out, along with the tiles on the walls and floor. From now on you don't have a bathroom.

3. Pipes, electrics and ventilation: about a week

The plumber moves the pipes and the waste and fits the shower drain, the electrician adjusts the electrics and ventilation goes in. This work ends up behind the tiles, so it has to be right now: afterwards you can't get to it without breaking things open.

4. Preparing and waterproofing: just over a week, with drying time

The walls and floor are levelled, then waterproofed.

Things have to dry in between: in the example, two working days after the preparation and one day after the waterproofing. How long it really needs depends on the material, so ask your tiler and don't let the tiling start earlier.

5. Tiling and grouting: about a week and a half

Tiling the walls and floor completely takes six working days in the example, followed by a day to dry before the grout goes in. If you only tile the shower area, it takes half the time.

6. Sanitary ware and shower screen: 3 days

Now the plumber comes back for the toilet, the basin and the taps, and the shower screen follows. From here on you can shower again.

7. Handover

Go through the bathroom with your builder. Whatever isn't right yet goes on your snagging list: a tile that sounds hollow, a sealant joint with a gap, a dripping tap. Write them down, with a date by which they'll be fixed.

Why the order matters so much

Say the tiler is booked but the plumber isn't finished. Then the tiler can't start and everything after moves with it: the drying time, the grouting, the sanitary ware and the handover. If you tile too early, something has to be broken open later.

In a good planning each trade therefore depends on the one before. If the plumber slips a few days, you see straight away when the tiler can come instead and can let them know in time.

In PLOTT every task sits on one timeline and depends on the task before it. If the pipework slips, the tiling and everything after it moves with it. The drying time sits behind the task as waiting time, so it doesn't get forgotten.

Read onRenovating a bathroom

Questions? Fair enough.

How long will I be without a bathroom?
In the example below, about five weeks, from taking out the old one until the toilet and taps are connected again. Sort out in advance where you'll shower.
Can a bathroom renovation go faster?
Yes, if you only freshen it up. Replacing taps and toilet, redoing the grout and sealant, and painting can be done in two to three weeks. Tiling only the shower area saves about a week too.
Which comes first, the plumber or the tiler?
The plumber. Pipes, drainage and the shower drain have to be in before the walls and floor are prepared and tiled. The plumber then comes back for the toilet, basin and taps.
How much extra time does underfloor heating take?
In PLOTT's example plan, about a week, because laying it comes before the pipework and the tiling.